Question: 1 / 400

How often are Program Increments (PIs) typically planned in SAFe?

Every week

Every month

Every 8 to 12 weeks

In the Scaled Agile Framework (SAFe), Program Increments (PIs) are typically planned every 8 to 12 weeks. This time frame allows Agile Release Trains (ARTs) to effectively deliver value to the business while ensuring adequate time for planning, execution, and review of the work to achieve the program’s objectives.

The 8 to 12-week planning cycle encompasses various activities, including PI planning events where multiple teams collaborate to identify and approach the objectives for the upcoming increment, and allocate resources and understand dependencies. Having a structured and consistent model helps teams align their work towards common goals and synchronize their efforts across the ART.

Planning PIs at this frequency enables teams to effectively respond to changes and adjust priorities, maintaining agility while ensuring there’s enough time to deliver meaningful increments of work. It strikes a balance between enough time to accomplish substantial work and maintaining the adaptability that Agile practices emphasize.

Get further explanation with Examzify DeepDiveBeta

Every 6 months

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy